Implemented projects
This section provides information on contracted EKII projects.
Back
The final beneficiary: |
Reliģiskās organizācijas "Rīgas Jēzus evaņģēliski luteriskā draudze" |
Project name: |
Energoefektivitātes paaugstināšana baznīcas ēkā |
The project contract date: |
2016.08.23 |
The total project costs (in EUR): |
564740.44 |
EKII / MF finansējuma apmērs (EUR): |
446144.90 |
Project completion date: |
2020.04.23 |
The project aims/activities: |
Name |
Type |
Attic insulation covering the ecowool wool 300 mm (after compaction) and coating the wind and precipitation retention diffusion. | Building insulation | Existing windows and external restoration, adjustment and sealing around the perimeter. The input nodes of internal entrance door leaf removal, replacement of a dense doors aizvērējmehānismiem. | General | Dome insulation with ecowool 200 mm thickness (after compaction) in constructive wooden frame and coating the wind and precipitation retention diffusion. | General | Piping insulation recovery basement. All the buildings of old radiator replacement. Installation of thermostatic valves for radiators. Infrared heater installation the church premises. | General | Old elektronistalācijas replacement and replacement of old lighting to LEDs | Lighting | The transition from district heating to a local autonomous heating, installation of gas generation pellet boiler SolarfocusPellettop 35 kW, as well as the installation of the boiler pump group and vacuum pellet storage and supply system. | Technology replacement | Dome architectural elements recovery | General | Existing heating systems reconstruction | General | construction supervision contract | General | author's contract | General | Thermography inspection, air permeability tests | General | Building energy certificate preparation | Energy audit | financial reserve | General |
Project description: |
|
Project implementation location |
|